Intercounty Connector (ICC)

The Intercounty Connector (ICC) is an 18 mile design-build multi-modal highway connecting I-270 and US 1 in Montgomery and Prince George’s counties.

Mega project corridor leadership

Intercounty Connector (ICC)

Design build multi modal highway connecting I 270 and US 1

Location: Montgomery County and Prince Georges County, Maryland
Length: 18 mile corridor
Client: Maryland State Highway Administration

The Intercounty Connector (ICC) is an 18 mile design build multi modal highway connecting I 270 and US 1 in Montgomery and Prince Georges counties. During project planning, The Wilson T. Ballard Company served as co General Engineering Consultant, taking a corridor wide lead on right of way, utilities, hydrologic and hydraulic analysis, air and noise analysis, and development of alignment options. WTB supported public outreach, coordinated avoidance and mitigation with the NEPA team, developed alternative cost estimates, and assisted SHA and FHWA with mega project cost estimate reviews.

Co General Engineering Consultant role
Right of way and utilities leadership
Air and noise corridor analysis

Planning phase corridor leadership

As co General Engineering Consultant during planning, WTB led several corridor wide technical efforts to support the identification and evaluation of ICC alternatives.

  • Corridor wide leadership in right of way and utility analysis
  • Hydrologic and hydraulic analysis to support alignment options
  • Air and noise analysis for multiple build alternatives
  • Development of alignment options and refinement in coordination with the NEPA team

WTB attended public outreach meetings and helped coordinate avoidance and mitigation options, while preparing cost estimates for alternatives and assisting SHA and FHWA in mega project cost estimate reviews.

Role during procurement and construction

As a major subconsultant to the GEC Joint Venture during procurement and construction, WTB continued to provide corridor wide leadership in key disciplines and design oversight.

  • Ongoing leadership in right of way, utilities, air and noise analysis
  • Overall design compliance oversight management for Contracts B and D/E Modified
  • Design compliance oversight for roadway and drainage design under Contract B
  • Support to SHA and the design build teams during procurement and construction

Environmental monitoring and mitigation

WTB supported environmental stewardship through independent monitoring and mitigation design along the corridor.

  • Provided an Independent Environmental Monitor for mitigation projects within the Northwest Branch
  • Assisted in management and design of environmental stewardship and compensatory mitigation projects
  • Coordinated with the NEPA and permitting teams to align design with environmental commitments

Stormwater and special protection area criteria

WTB was instrumental in developing design criteria related to stormwater treatment within Montgomery County Special Protection Areas, particularly for sensitive tributaries.

  • Development of stormwater treatment criteria for the Paint Branch Special Protection Area
  • Development of stormwater treatment criteria for the Gum Springs tributary Special Protection Area
  • Integration of these criteria into project wide design performance specifications

Interchange and intersection design performance

WTB contributed to the development of design performance specifications for key ICC interchanges and intersections.

  • Design performance specifications for the ICC and MD 650 single point urban interchange (SPUI)
  • Design performance specifications for the ICC and US 1 continuous flow intersection (CFI)
  • Support for innovative interchange forms that balance capacity, safety, and context

Recognition and project success

Throughout design and construction, the ICC and GEC team received numerous awards recognizing technical excellence and project delivery.

  • Multiple awards from engineering and transportation organizations
  • Most recent recognition as Engineering Society of Baltimore 2015 Project of the Year

Awards and recognition

The ICC and the General Engineering Consultant team received several awards for innovation, environmental stewardship, and overall project delivery. Below are representative awards associated with the corridor.

ICC project award 1
ICC project award 2
ICC project award 3
Result: ICC delivered as a major regional corridor that improves east west mobility, incorporates innovative design solutions, and has been recognized by the Engineering Society of Baltimore and other organizations for engineering excellence.