Baden Naylor Road Bridge Replacement
On September 7, 2011, the north abutment of Bridge No. P-403 (Baden Naylor Road over Rock Creek) was severely undermined due to scour, resulting in the loss of the abutment and collapse of the bridge and approach roadway during Tropical Storm Lee.
Baden Naylor Road Bridge Replacement over Rock Creek
Fast tracked replacement of Bridge No. P-403 following Tropical Storm Lee
On September 7, 2011 the north abutment of Bridge No. P-403 on Baden Naylor Road over Rock Creek was severely undermined by scour during Tropical Storm Lee. The resulting loss of the abutment caused collapse of the bridge and approach roadway, which closed Baden Naylor Road and created more than a six mile detour for local traffic. The existing structure was a single lane, two span continuous reinforced concrete slab bridge on spread footings.
Project photos
Fast track delivery approach
In late 2011 Prince Georges County DPW and T established a fast track project using on call engineering consultant The Wilson T. Ballard Company and on call bridge contractor Rustler Construction, Inc. The design team also included AB Consultants, Inc. to provide survey control, geotechnical investigation, and roadway, stormwater management, storm drainage, and erosion and sediment control design.
- On call engineering and construction partners engaged quickly
- Multi firm design team assembled to address all disciplines
- Priority on restoring access and minimizing detours
Comprehensive engineering services
The project required a full range of engineering and environmental services in order to replace the structure and approach roadway on an accelerated schedule.
- Wetland identification and field surveys for topography, stream sections, property, and borings
- Deed research and preparation of property mosaic, right of way plats, and metes and bounds descriptions
- Utility coordination and participation in wetland jurisdictional review
- Hydrologic and hydraulic analysis for out of kind structure replacement
- Environmental documentation and coordination with reviewing agencies
- Foundation and scour analysis, preliminary and final bridge design
- Contract plans, specifications, and engineers cost estimate development
- Participation in County review meetings, shop drawing review, and construction consultation
Superstructure selection
During preliminary design, fabricators were contacted to compare availability, cost, and delivery time for prestressed concrete and structural steel superstructures.
- Evaluated prestressed concrete box beams against structural steel options
- Prestressed concrete box beams offered lower cost and one third of the delivery time
- County selected a single span, 72 foot long prestressed concrete box beam alternative in March 2012
- Design team advanced Semi Final plans immediately after structure type selection
Schedule, procurement, and construction
At the Semi Final stage the County began negotiating project costs with the contractor. Notice to proceed for construction was issued on December 3, 2012, with a contract duration of 180 calendar days.
- Design notice to proceed to bridge opening in roughly 15 months
- Construction substantially complete and open to traffic by late June 2013
- Approximately 18 months total to design, permit, acquire right of way, relocate utilities, remove the existing structure, and construct the new bridge and approaches, including in stream restrictions
Team coordination and community focus
Close coordination among the County, consultants, reviewing agencies, utility owners, contractor, and adjacent landowners was essential to restoring the road as quickly as possible.
- Regular communication among all project partners
- Collaborative development of unique strategies and solutions to address schedule constraints
- Responsiveness to community concerns about detours and access
- Delivery of a hydraulically appropriate bridge that improves long term resilience
Recognition and project outcome
The completed Baden Naylor Road bridge replacement met the County goal of restoring service on an accelerated schedule while providing a more robust structure for future storm events.
- Road reopened with a larger and hydraulically appropriate bridge
- Improved approach roadway and relocated utilities completed within the compressed timeframe
- Project recognized for excellence in planning, design, and delivery