Harry S. Truman Drive bridge over Southwest Branch

Award: 2025 CEAM Award of Merit

Client: Prince George’s County DPW&T

Construction cost: $5,045,000

Substantially completed: May 19, 2025

2025 CEAM Award of Merit

The Wilson T. Ballard Company is proud to have assisted the Prince George’s County Department of Public Works and Transportation with the Harry S. Truman Drive bridge project.

The rehabilitation of Bridge No. P-0581, Harry S. Truman Drive over Southwest Branch, received the 2025 County Engineers Association of Maryland Award of Merit for large projects.

Bridge Condition and Emergency Response

During WTB’s annual condition inspection of Bridge P-0581 in February 2018, the beams were determined to be in serious condition. The existing bridge, constructed in 1974 and rehabilitated in 2014, was a two-span, 84-foot-long prestressed concrete voided slab bridge with a hot-mix asphalt wearing surface. The bridge carried the four-lane Harry S. Truman Drive roadway over Southwest Branch.

Water stains and leakage were present throughout the underside of the beams and at the joints between them. Cracking was also observed on the beams. The prestressing strands had up to 90% section loss, while the stirrups had up to 100% section loss.

The left northbound lane was closed to traffic, and the bridge’s posted weight limit was lowered due to the beam defects. Because of the severity of the superstructure deterioration and the potential risk of bridge failure, DPW&T engaged WTB to design emergency temporary supports so the northbound lane could be reopened.

Testing and Engineering Services

The County and its consultant developed and implemented an extensive material-testing program to determine the condition of the existing bridge. Testing showed that accelerated corrosion was occurring at the reinforcing steel in the pier cap to a depth of five inches, necessitating replacement of the pier cap.

The project required a full range of engineering services, including:

  • Wetland identification
  • Preparation of right-of-way plats and metes-and-bounds descriptions
  • Property and easement acquisition
  • Coordination with utility companies
  • Hydrologic and hydraulic analysis for in-kind structure replacement
  • Environmental documentation
  • Stormwater management design
  • Coordination with reviewing agencies
  • Soil borings, foundation design, and scour assessment
  • Final bridge and roadway design
  • AASHTO review
  • Maintenance of stream flow and traffic design
  • Preparation of contract plans, specifications, and the engineer’s cost estimate

Environmental Services

Environmental services for the Harry S. Truman Bridge rehabilitation included wetland and waterway delineation, an agency field review, and preparation of a waterway permit application.

The work also included a field review and preparation of a Natural Resource Inventory equivalency and Woodland Conservation Ordinance Exemption Letter request, agency coordination regarding the protection of instream species, and National Environmental Policy Act compliance.

Cost-Saving Design Solutions

To reduce costs and expedite Maryland Department of the Environment permit approval, the existing 20-inch-diameter tapered pipe piles were retained and incorporated into the new pier bent.

The existing abutments and concrete slope protection were also retained. New abutments were constructed behind the existing structures and supported on 20-inch-diameter concrete-filled pipe piles. This approach allowed construction to proceed with minimal stream diversion and environmental impacts.

Completion Ahead of Schedule and Under Budget

The project’s total construction cost was $5,045,000. The contractor received Notice to Proceed on December 13, 2023. Construction was substantially completed on May 19, 2025, ahead of schedule and under budget.

This project is an excellent example of the County, consultants, reviewing agencies, utility owners, contractors, and adjacent landowners working together to replace a severely deteriorated bridge as quickly as possible. The project team developed an outstanding replacement solution that addressed the mobility and safety needs of the local community.